Current & Future Projects


 

2025

     

B25 - Sal Street & Industrial Drive

UPDATE: Wednesday, May 28, 2025

Construction consists of removal and replacement of the storm sewer, roadway surface, curb and gutter and driveway aprons and a new storm water retention pond.

Project Timeline
Construction: April - September 2025

Two Week Outlook:

  • Week of May 26th: Continuation of storm sewer installation on Sal Street. Work will start on Industrial Drive, East of Bellevue Street later this week.
  • Week of June 2nd: Continuation of storm sewer installation on Industrial Drive, East of Bellevue Street along with through the utility easement, pending timing of the relocation of existing utilities through the easement. The Contractor will also begin roadway and driveway removals on Sal Street and Industrial Drive, West of Bellevue Street. Driveways that are removed, will be temporarily filled with gravel, ensuring vehicle access, until the permanent replacement.

Important Dates

  • 04/28: Start of Construction, West of Bellevue Street
  • 06/02: Start of Construction, East of Bellevue Street
  • 07/11: End of Construction, West of Bellevue Street
  • 08/22: End of Construction, East of Bellevue Street

Road Closures, Vehicles & Traffic
For construction a minimum of 1 travel lane is to remain open at all times. Slight delays may be encountered due to construction equipment using the area. Be attentive of construction workers through the construction zone. During the crossing of Bellevue Street on Sal Street, a small local detour is anticipated and will be signed accordingly.

Business Access
Business access will be maintained as much as possible during construction. We intend to keep driveways open to each business at all times but may need to temporarily close one due to storm sewer installation. Driveway replacements will be done while allowing access during replacement. Prior communication will occur if access will be unobtainable. Please contact the Construction Manager if you require special access needs.

Communication

It is the intent of the Village to minimize the amount of disruption and inconvenience to the community during any construction process. If during normal work hours you feel something went unnoticed, or needs attention, please contact Cedar Corporation. As project inspector, Cedar Corporation is most familiar with the daily operations of construction and can quickly resolve many issues.

As always, in an emergency, please call 911.


Project Updates

Construction updates will be posted on the Village website bi-weekly, and when major changes will be occurring. If at any time you would like additional information, please call Teal at 920-593-5507 or Kyle at 920-785-7308.

Informational Meeting Documentation

Presentation

2025

     

A25 Reconstruction & C25 Reconditioning

UPDATE: Wednesday, May 28, 2025

IF YOU SEE WOOD STAKES OR UTILITY FLAGS ALONG YOUR PROPERTY, PLEASE LEAVE THEM UNTIL CONSTRUCTION IS COMPLETE.

MCC, Inc will be performing Project A25 which consists of curb and gutter replacements (starting in April), miscellaneous utility structure reconstructions and asphalt resurfacing. Project C25 consists of Hot-In-Place Asphalt Recycling (H.I.R.) prior to the final surface layer of asphalt being placed by Project A25.

Project Timeline
Construction: April - July 2025

Project Roads & Work Expected

  • Mac Ln. (Bluestone Pl. – Hazen Rd.) & Mac Ct.:
    Curb Patching, Structure Adjustments, Surface Asphalt Layer (A25)
    H.I.R. after curb patching and structure adjustments (C25)
  • Kane Ln. (Elben Ct. – VandenBergh Pl.):
    Curb Patching, Structure Adjustments, Surface Asphalt Layer (A25)

    H.I.R. after curb patching and structure adjustments (C25)
  • Keehan Ln. (Bluestone Pl. – Elben Ct.):
    Curb Patching, Structure Adjustments, Surface Asphalt Layer (A25)
    H.I.R. after curb patching and structure adjustments (C25)
  • Elben Ct. (In Entirety):
    Curb Patching, Structure Adjustments, Surface Asphalt Layer (A25)
    H.I.R. after curb patching and structure adjustments (C25)
  • Guns St. (Allouez Ave. – Kensington Ln.), Sunnymede Ln (In Entirety) & Kensington Ln. (In Entirety):
    Curb Patching, Structure Adjustments, Surface Asphalt Layer (A25)
    H.I.R. after curb patching and structure adjustments (C25)
  • Lynwood Ln. (Verlin Rd. – Guns St.), Nellie Ln., Nellie Ct., Pauly Ct., Lynwood Ct. (In Entirety):
    Curb Patching, Structure Adjustments, Surface Asphalt Layer (A25)
    H.I.R. after curb patching and structure adjustments (C25)
  • Seville Dr. (In Entirety) & Eldorado Dr. (Seville Dr. – Verlin Rd.):
    Curb Patching, Structure Adjustments, Surface Asphalt Layer (A25)
    H.I.R. after curb patching and structure adjustments (C25)
  • Eldorado Dr. (Bellevue St. – Seville Dr.):
    Curb Patching, Roadway Reconstruction and Traffic Calming (A25)
  • Bluestone Pl. (Hazen Rd. – 500’ South of VandenBergh Pl.):
    Curb Patching, Structure Adjustments and Roadway Reconstruction (A25)
  • VandenBergh Pl. (Keehan Ln. – Bluestone Pl.):
    Curb Patching, Structure Adjustments and Roadway Reconstruction (A25)
  • Skyview St. (Lime Kiln Rd. – Hazen Rd.):
    Curb Patching, Structure Adjustments and Roadway Reconstruction (A25)

Two Week Outlook: Start of Contract A-25 Work on April 14

  • Week of May 26th: Completion of structure repairs and fine grading on Skyview Street, with the possibility of paving, weather dependent. Crews will also continue with concrete repairs on Eldorado Drive. Asphalt removal and rough grading will occur on Bluestone Place.
  • Week of June 2nd: Continuation of paving on Skyview Street, Stabilization and final grading of Bluestone Place aggregate, continuation of concrete work on Eldorado Drive and miscellaneous repairs throughout the project.

Important Dates

  • 04/14: Start of Construction (A-25)
  • 05/30: Completion of Utilities & Concrete (A-25)
  • 06/09: Start of Construction (C-25)
  • 07/16: Completion of HIR (C-25) & Start Surface Layer Asphalt on HIR Road (A-25)
  • 07/31:Approximate Completion of Work (A25)

Communication
It is the intent of the Village to minimize the amount of disruption and inconvenience to the community during any construction process. If during normal work hours you feel something went unnoticed, or needs attention, please contact Cedar Corporation. As project inspector, Cedar Corporation is most familiar with the daily operations of construction and can quickly resolve many issues. As always, in an emergency, please call 911.

Project Updates

Construction updates will be posted on the Village website bi-weekly, and when major changes will be occurring. If at any time you would like additional information, please call Teal at 920-593-5507 or Kyle at 920-785-7308.

Informational Meeting Documentation


2026

     

Hoffman Road
Bellevue St. to Monroe Rd.

UPDATE: Monday, May 20, 2024

The proposed project would involve improvements to the 0.7-mile section of Hoffman Road between Bellevue Street (County XX) and Monroe Road (County GV). The project is located on the west side of the Village of Bellevue in Brown County.

Public Involvement Meeting
May 15, 2024 - July 5, 2024
Presentation
Public Comment Form


Project Schedule
Public Involvement - May 15, 2024 - July 5, 2024
Preliminary Plans - April 2024
Environmental Document - July 2024
Final Plans - August 2025
Construction would be scheduled for 2026

2026

     

Ontario Road Reconstruction
Eaton Rd to North Village Limits

UPDATE: Monday, May 20, 2024

The proposed project would involve improvements to an approximately 0.50-mi. segment of Ontario Road between Eaton Road (County JJ) and the North Village Limits. The project is located on the east side of the Village of Bellevue in Brown County.

Public Involvement Meeting
May 15, 2024 - July 5, 2024
Presentation
Public Comment Form


Project Schedule
Public Involvement - May 15, 2024 - July 5, 2024
Preliminary Plans - March 2024
Environmental Document - August 2025
Construction would be scheduled for 2026