UPDATE: Wednesday, May 28, 2025
IF YOU SEE WOOD STAKES OR UTILITY FLAGS ALONG YOUR PROPERTY, PLEASE LEAVE THEM UNTIL CONSTRUCTION IS COMPLETE.
MCC, Inc will be performing Project A25 which consists of curb and gutter replacements (starting in April), miscellaneous utility structure reconstructions and asphalt resurfacing. Project C25 consists of Hot-In-Place Asphalt Recycling (H.I.R.) prior to the final surface layer of asphalt being placed by Project A25.
Project Timeline
Construction: April - July 2025
Project Roads & Work Expected
- Mac Ln. (Bluestone Pl. – Hazen Rd.) & Mac Ct.:
Curb Patching, Structure Adjustments, Surface Asphalt Layer (A25)
H.I.R. after curb patching and structure adjustments (C25)
- Kane Ln. (Elben Ct. – VandenBergh Pl.):
Curb Patching, Structure Adjustments, Surface Asphalt Layer (A25)
H.I.R. after curb patching and structure adjustments (C25)
- Keehan Ln. (Bluestone Pl. – Elben Ct.):
Curb Patching, Structure Adjustments, Surface Asphalt Layer (A25)
H.I.R. after curb patching and structure adjustments (C25)
- Elben Ct. (In Entirety):
Curb Patching, Structure Adjustments, Surface Asphalt Layer (A25)
H.I.R. after curb patching and structure adjustments (C25)
- Guns St. (Allouez Ave. – Kensington Ln.), Sunnymede Ln (In Entirety) & Kensington Ln. (In Entirety):
Curb Patching, Structure Adjustments, Surface Asphalt Layer (A25)
H.I.R. after curb patching and structure adjustments (C25)
- Lynwood Ln. (Verlin Rd. – Guns St.), Nellie Ln., Nellie Ct., Pauly Ct., Lynwood Ct. (In Entirety):
Curb Patching, Structure Adjustments, Surface Asphalt Layer (A25)
H.I.R. after curb patching and structure adjustments (C25)
- Seville Dr. (In Entirety) & Eldorado Dr. (Seville Dr. – Verlin Rd.):
Curb Patching, Structure Adjustments, Surface Asphalt Layer (A25)
H.I.R. after curb patching and structure adjustments (C25)
- Eldorado Dr. (Bellevue St. – Seville Dr.):
Curb Patching, Roadway Reconstruction and Traffic Calming (A25)
- Bluestone Pl. (Hazen Rd. – 500’ South of VandenBergh Pl.):
Curb Patching, Structure Adjustments and Roadway Reconstruction (A25)
- VandenBergh Pl. (Keehan Ln. – Bluestone Pl.):
Curb Patching, Structure Adjustments and Roadway Reconstruction (A25)
- Skyview St. (Lime Kiln Rd. – Hazen Rd.):
Curb Patching, Structure Adjustments and Roadway Reconstruction (A25)
Two Week Outlook: Start of Contract A-25 Work on April 14
- Week of May 26th: Completion of structure repairs and fine grading on Skyview Street, with the possibility of paving, weather dependent. Crews will also continue with concrete repairs on Eldorado Drive. Asphalt removal and rough grading will occur on Bluestone Place.
- Week of June 2nd: Continuation of paving on Skyview Street, Stabilization and final grading of Bluestone Place aggregate, continuation of concrete work on Eldorado Drive and miscellaneous repairs throughout the project.
Important Dates
- 04/14: Start of Construction (A-25)
- 05/30: Completion of Utilities & Concrete (A-25)
- 06/09: Start of Construction (C-25)
- 07/16: Completion of HIR (C-25) & Start Surface Layer Asphalt on HIR Road (A-25)
- 07/31:Approximate Completion of Work (A25)
Communication
It is the intent of the Village to minimize the amount of disruption and inconvenience to the community during any construction process. If during normal work hours you feel something went unnoticed, or needs attention, please contact Cedar Corporation. As project inspector, Cedar Corporation is most familiar with the daily operations of construction and can quickly resolve many issues. As always, in an emergency, please call 911.
Project Updates
Construction updates will be posted on the Village website bi-weekly, and when major changes will be occurring. If at any time you would like additional information, please call Teal at 920-593-5507 or Kyle at 920-785-7308.
Informational Meeting Documentation
|