As the Village continues to add residential housing in the eastern portion of Bellevue, there is a need for additional recreational amenities. One amenity which has been included in all Comprehensive Outdoor Recreation Plans since 2011 is a pedestrian trail that connects Ontario and Huron Rd. to the north of JJ. A trail in this location would connect highly saturated residential areas around the Whispering Willow subdivision with the Huron Rd trail as well as other amenities like Bellin and the YMCA.


Project Overview:

TAP


Project Timeline/Schedule
:
 1/28/2026   Operational Planning Meeting  
 1/28/2026   30% Plan Review 
 2/25/2026   1st Public Informational Meeting
 March/April 2026   Environmental Document 
 April 2026   60% Plan Review, Design Study Report
 April 2026   Right of Way Plat & Descriptions 
 June 2026   2nd Public Involvement Meeting
 9/1/2026   90% PS&E
 11/1/2026   Final PS&E 
 March 2027   Letting Date
 Summer 2027   Begin Construction

Public Information Meeting 
Wednesday, February 25, 2026
5:00 - 6:00 PM
Village Hall Training Room - 3100 Eaton Rd

Public Information Meeting Flyer
Ontario-Huron Trail DESIGN-Roll Plot
45160000_PIM_PP Sheets
2026-30 CIP Ontario-Huron Cutsheet
30% Draft Plan
4516-00-00_Comment Form
Public Information Meeting Presentation