Project Description:
As the Village continues to add residential housing in the eastern portion of Bellevue, there is a need for additional recreational amenities. One amenity which has been included in all Comprehensive Outdoor Recreation Plans since 2011 is a pedestrian trail that connects Ontario and Huron Rd. to the north of JJ. A trail in this location would connect highly saturated residential areas around the Whispering Willow subdivision with the Huron Rd trail as well as other amenities like Bellin and the YMCA.
Project Overview:
Project Timeline/Schedule:
| 1/28/2026 |
Operational Planning Meeting |
| 1/28/2026 |
30% Plan Review |
| 2/25/2026 |
1st Public Informational Meeting |
| March/April 2026 |
Environmental Document |
| April 2026 |
60% Plan Review, Design Study Report |
| April 2026 |
Right of Way Plat & Descriptions |
| June 2026 |
2nd Public Involvement Meeting |
| 9/1/2026 |
90% PS&E |
| 11/1/2026 |
Final PS&E |
| March 2027 |
Letting Date |
| Summer 2027 |
Begin Construction |
Public Information Meeting
Wednesday, February 25, 2026
5:00 - 6:00 PM
Village Hall Training Room - 3100 Eaton Rd
Public Information Meeting Flyer
Ontario-Huron Trail DESIGN-Roll Plot
45160000_PIM_PP Sheets
2026-30 CIP Ontario-Huron Cutsheet
30% Draft Plan
4516-00-00_Comment Form
Public Information Meeting Presentation